Dear Experts,
We have a 3 system landscape – Development (DEV), Quality (QAS) & Production (PRD) system.
We have identified the security notes from ST13->RSECNOTE tool for each system & were able to find the common notes for all 3 systems.
1->Please let us know the sequence in which we need to apply the notes? Date wise or note number wise (increasing order)
2->Also can we club the common notes in one transport request and then transport it in all 3 systems ?
As per custom, we would be applying security notes starting from DEV->QAS->PRD.
Issue is , we found some notes which are different for each system. Please guide how do we proceed ?
Whether to import the uncommon notes first or common notes, or in total sequence for each system independently ?
3->By clicking the ‘check side effects button’ We were able to also find some list of notes. These must be the side effects notes of previously applied notes…Should these notes also be implemented first ?
4-> We are also able to see different corrections section as per release version in most of the notes.Should we implement the note(containing all the corrections release wise) or the correction corresponding to the release of our system (in this case we should download the correction only and not the note then ? )
Please guide me...
Regards
Imaan